Construction is continuing on 34 kilometers of the metro rail system, which are scheduled to go into operation in early 2009. When the new metro lines open up for use, the share of mass transport represented by the metro in İstanbul will rise from 9 percent to 13 percent.

The İstanbul Municipality has completed construction and electrical work on the Taksim-Yenikapı metro's Şişhane section, and work is nearly complete on the Otogar-Bağcılar-Kirazlı, Kirazlı-Olimpiyat Köyü, Topkapı-Edirnekapı and 4.Levent-Darüşşafaka metro lines. The 34 kilometers covered by these five lines, which are all scheduled to be up and running by February, will bring the total length of the entire system to 97 kilometers.

Test runs were done on Oct. 29 on the Taksim-Şişhane and 4.Levent-Darüşşafaka metro lines, which will be opened to the public at the start of the new year. Test runs will be done on the 5.6-kilometer Otogar-Bağcılar-Kirazlı line, the 15.9-kilometer Kirazlı-Başak Konutları-Olimpiyat Köyü line and the 2.2-kilometer Topkapı-Edirnekapı rail system within the next two weeks.

İstanbul Mayor Kadir Topbaş has allocated YTL 11.5 billion for transportation in the city over his past four-and-a-half years as mayor out of a total of YTL 22.5 billion in investment for the city. " Our construction work on 66 kilometers of metro lines is continuing at full speed. Transportation flow and movement within the city at large is now three times what it was when I came to power," noted Topbaş.

Two more metro lines to be constructed

The İstanbul Municipality is scheduled to start construction next year on the 19-kilometer Üsküdar-Altunizade-Ümraniye-Dudullu-Samandıra-Taşdelen light rail system, which authorities note will have a significant impact on the state of transportation on the Anatolian side of İstanbul. Construction is expected to cost $950 million for the line, which is anticipated to carry 45,000 passengers in each direction every hour.

On the European side of İstanbul, the municipality is accepting bids for the construction of a light rail system planned for Bakırköy-Şirinevler-Sefaköy-Avcılar-Beylikdüzü. The system will be 25 kilometers in length, and its foundation will be laid this coming year once the job has been awarded to the successful bidder. The anticipated cost of this line, which will also carry around 45,000 passengers in each direction every hour, will be around $1.35 billion. Both this line and the Üsküdar-Samandıra line are expected to be completed some time within the year 2012.

Real Metrobuses to run in February

Trial runs of the vehicles to be used in İstanbul's Metrobus line are complete, and the " real" Metrobuses will enter into operation in February 2009, İstanbul Transportation Authority (İETT) head Mehmet Öztürk has said.

They're not called Metrobuses, but Phileas brand vehicles, Öztürk announced on Wednesday. The Metrobus, a new transportation line in İstanbul that integrates with the underground metro and regular city bus systems, has so far run using normal city buses, but in February the special Phileas vehicles, described as " trams on wheels," will enter into service. Testing of the vehicles took place after midnight for 28 days, Öztürk said, to fulfill the Transportation Ministry's pre-approval trial requirements. Transportation Ministry officials supervised the trial runs, he said. Compared to normal city buses, the Phileas vehicles use 40 percent less fuel, he noted.February's opening of the Zincirlikuyu-Soğütlüçeşme segment of the Metrobus line will see the operation of the new Metrobus models exclusively. İstanbul Today's Zaman

YASİN KILIÇ İSTANBUL